Hawkfield GAA Newbridge

Project: Gym

Client: Hawkfield GAA Newbridge

Project Description

  • Excavated foundations, blinding and backfilled around rising walls for floor slabs. 
  • Stone to be placed to correct level and compacted by use of vibrating plate. Stone sub base ,   blinded with sand. Crew to lay geotextile on top of sand base.
  • Radon sumps and membrane.
  • Steel fixing and shuttering/ Pouring and finishing of insulated concrete slab.
  • Care will be taken in moving concrete vibrator from place to place 
  • Rotation/breaks to be deployed for operatives using the concrete poker 
  • Underground foul and storm drainage: Reduce ground to required level, Shutter for pads if .  Pour concrete, Carry out drainage alteration to storm line, excavate down to pipeline . Install manhole and raise lid to required level.

Key Challenges

  • Working at height – roofs and steel structure
  • Big concrete area poured the concrete floor

If you would like to discuss your upcoming project with an experienced and trusted team, call us now on 01-4595390 or email info@kendra.ie.